Almaty International Airport reopens modernized domestic terminal

Photo: t.me/caa_kaz

Almaty International Airport has officially opened Terminal 1 (T1), which serves domestic flights, following a major renovation. Around $32 million was invested in the project. The upgraded terminal can now handle up to 9 million passengers a year.

The renovation began in September 2025 and took 13 months to complete. The project was carried out as part of the Horizon programme, which sets out the airport’s development plans through 2050.

As part of the upgrade, the check-in area was completely renovated and 23 new check-in counters were installed. The pre-flight security screening area was expanded, increasing the width of the passenger screening passage from 2 metres to 3.5 metres. The number of automated boarding-pass scanning gates rose from three to five.

All eight boarding gates were upgraded, and the number of seats in the waiting areas was increased. Three new passenger boarding bridges were also installed.

The baggage handling infrastructure was upgraded as well. The total length of baggage conveyor belts increased from 85 to 228 metres. A modern screening system was introduced, allowing security staff to view the contents of baggage in 3D. The terminal’s engineering systems, elevators and restrooms were also renovated.

According to the airport, when all passengers were previously served in a single terminal building, its capacity was approximately 3.2 million passengers a year. The upgraded domestic terminal can now handle up to 9 million passengers annually.

The Horizon programme goes beyond the renovation of Terminal 1. Other projects include the construction of a new taxiway, the reconstruction of one of the runways, the development of the cargo apron and the construction of an aircraft maintenance hangar. The programme also includes the construction of Central Asia’s first specialized aircraft de-icing facility.